Shutdown & production plans
Company AMember companies publish their turnaround windows to each other so parts demand can be planned across the group. Unlike stock levels, these plans are shared deliberately — that is the point of the arrangement.
Your next shutdown
Company A
Reading the current date…
Overlapping shutdowns
Competing demand for the same parts
Reading the current date…
Twelve-month plan
- Production
- Ramp-up
- Shutdown
Published plans
Company A
YouToday: reading the current date…
14 Sep 2026Confirmed
Unit 200 — pump train overhaul
14 days · ends 27 Sep 2026
8 Mar 2027Planned
Electrical substation inspection
7 days · ends 14 Mar 2027
Company B
Today: reading the current date…
28 Sep 2026Confirmed
Boiler and heat exchanger cleaning
21 days · ends 18 Oct 2026
26 Apr 2027Planned
Filtration and strainer replacement
9 days · ends 4 May 2027
Company C
Today: reading the current date…
21 Sep 2026Confirmed
Valve overhaul — process train 3
10 days · ends 30 Sep 2026
21 Apr 2027Planned
Instrumentation recertification
12 days · ends 2 May 2027